The steps

  1. Check the parcelLook up your lot in ZIMAS: zone, Hillside Area, fire zone and any specific plan or overlay. Hillside fire-zone lots and the Mulholland corridor add steps; see Hillside & fire zones.
  2. Prepare drawingsSite plan, floor plan, elevations, structural details and Title 24 energy compliance. Garage conversions also document the existing structure.
  3. SubmitOnline through ePlanLA, or in person by appointment.
  4. Plan check and clearancesLADBS reviews the building code and routes clearances: Bureau of Engineering (sewer availability, roof drainage, address), LA Fire Department (hydrants and access), City Planning (zoning), and LADWP if the work is within 10 ft of a utility easement.
  5. Permit issuedPay fees, including school fees for units over 500 sq ft.
  6. Build and inspectLADBS inspections through final, then the certificate of occupancy.

Source: LADBS IB P/BC 2026-150.

Review deadlines

State law puts LADBS on a clock: (Gov. Code § 66317)

  • 15 business days to say whether the application is complete. If it doesn't, the application is deemed complete.
  • 60 days from a complete application to approve or deny it, or it is deemed approved.
  • The City must have an appeal process that decides within 60 business days.

The clock runs on a complete application. Corrections you resubmit, and clearances from other departments, are where most projects lose time.

Pre-approved standard plans

LADBS keeps a catalog of ADU Standard Plans already reviewed for the building code. The current list has 30 plans, from 280 to 1,200 sq ft and studio to three bedrooms. You buy the drawings from the firm that owns them; the City's own YOU-ADU is a 455 sq ft one-bedroom. Plan check still reviews your site: zoning, setbacks, foundation and utilities. (LADBS ADU Standard Plans)

Standard plans fit backyard ADUs. A garage conversion works with the garage you have, so it is drawn for your property.

Fees

  • LADBS plan check and permit fees, based on the work.
  • Impact fees only above 750 sq ft, proportional to the main house; no park fees or Affordable Housing Linkage Fee on ADUs.
  • LAUSD school fees of $5.38 per sq ft on ADUs over 500 sq ft.

See fees under the rules for the citations.

Utilities and address

LADWP serves a lot with one electric service, and meters are grouped at the main house. If the ADU gets its own meter, it needs its own address approved by Public Works. (LADWP Electric Service Requirements, 2025 ed., § M) Sewer availability is cleared by the Bureau of Engineering during plan check.

Where to go

The LADBS Van Nuys office handles plan check, permits and inspections for the Valley: 6262 Van Nuys Blvd, Van Nuys, CA 91401. Most ADU applications are filed online through ePlanLA.

Sources

Questions homeowners ask

How long does an ADU permit take in Los Angeles?
LADBS must say whether an application is complete within 15 business days and approve or deny a complete application within 60 days. Corrections and department clearances add time.
Can I use a pre-approved ADU plan in Sherman Oaks?
Yes, for a new ADU. LADBS lists about 30 Standard Plans from 280 to 1,200 sq ft. Your site is still reviewed for zoning, setbacks, foundation and utilities.
Which LADBS office serves Sherman Oaks?
The Van Nuys office at 6262 Van Nuys Blvd, though most ADU applications are submitted online through ePlanLA.

Plan first, then permit

See what fits your Sherman Oaks garage or backyard.

Measure the space, pick a layout and get a preliminary floor plan, concept photo and one-sheet in a few minutes. Free, no obligation.

Garage conversions, JADUs and backyard ADUs. Start with the space you have; refine it any time.

Start My Free ADU Plan